Operator Updates for MHR Storage and Refurbishment
Update: Fleet Update 22/4: Stuff has been moved through the standard refurb process, but the e200s, citywides, and the SB200s are taking longer than expected. the 3 200mmcs here are being done up for an external customer.
Update: 200MMCs being transferred to Sligo for 712.
Update: Status Update for fleet at 21/4: E200s fully stripped down, inspections OK, getting rebuilt. E400/MMCs: being stripped down. Citywide: Battery swap in process, interior in progress. Liner: Batteryswap, interior to do. BZL: Batteryswap, interior to do. MAN E200s: Sourcing engines, otherwise in same phase as integral E200s. 200MMCs: Ready for transfer.
Update: Acquiring E400s for refurbishment to send to new depot.
Update: BYD BD11 GXL67 transferred to Cherrywood for maintenance after major electrical fault
Update: Entity established for storage and refurbishment of vehicles.